.... Specialising in reducing accelerated erosion

Installation of Vegetated Riprap

TECK COMINCO METALS LTD RIVERBANK RESTORATION PROJECT

Go To:

Riverbank Section 1

Riverbank Sections 2 and 1A

Survival and Growth

Main Riverbank Restoration Project Page

Location: Bank of Columbia River adjacent to the Teck Cominco lead-zinc smelter in Trail, BC

Client: Teck Cominco Metals Limited

Objective: Creation of fish and wildlife habitat by establishing vegetation within riprap revetment during road construction.

The live cuttings used in the vegetated riprap applications described below consisted of the following willow species (Salix bebbiana/scouleriana/exigua) and (Salix lucida ssp. lasiandra). Black Cottonwood (Populus balsamifera ssp. trichocarpa) and Red-Osier Dogwood (Cornus stolonifera).

Riverbank Section 1:

 

In the installation of Section 1, live cutting pockets and a vegetated riprap brush layer technique were used.

 

A riprap toe apron was first constructed within the river to support the additional riprap placed on the bank above. A gravel layer was placed over the original excavated bank in order to provide filtration of fine sediment from entering the river. The first lift or layer of riprap was then placed and live cutting pockets were inserted into the bank above using an excavator and manual labour.

 

Each pocket consisted of six cuttings contained within two protective sleeves, slit to allow future expansion as stems grow. For each pocket the excavator opened a planting hole, into which the base of the cuttings were placed manually along with water and custom soil amendments. The plastic sleeves were positioned so that the cuttings were protected when the next lift of riprap was placed above. A total of four rows of live cutting pockets were installed. A final lift of riprap was placed above the highest rows. The elevation of each row of pockets was maintained using a laser level as work progressed.

 

To construct the vegetated riprap brush layer, a trench was dug into the road sub-grade behind the last lift of riprap. Live cuttings were laid out along this trench so that the tips protruded above the adjacent riprap. Water, topsoil and soil amendments were added prior to backfilling of the trench using native soil material. Protective wooden boards/sheets were then placed over the lower portion of the exposed cuttings as protection and final rock was placed to raise the road to the desired sub-grade.

 
 
Construction of Section 1 toe apron, spring 2006

Construction of Section 1 toe apron, spring 2006

First lift of riprap placed,
gravel filter placed on bank

First lift of riprap placed, gravel filter placed on bank

 

Inserting live cutting pocket and watering

Inserting live cutting pocket and watering

   
Inserting live cutting pocket
Inserting live cutting pocket
Placing next lift of riprap

Placing next lift of riprap

Inserting live cutting pockets

Inserting live cutting pockets

Checking elevation of riprap

Checking elevation of riprap

   
 
Excavated trench for vegetated riprap

Excavated trench for vegetated riprap

Live cuttings placed in trench, trench being backfilled with topsoil and native soil material

Live cuttings placed in trench, trench being backfilled with topsoil and native soil material

 
Protective wooden sheets placed

Protective wooden sheets placed

Placing riprap to final road sub-grade

Placing riprap to final road sub-grade

 

Riverbank Sections 2 and 1A:

 

Vegetated riprap in Sections 2, constructed in 2006, and 1A, constructed in 2008, consisted of only one row of the brush layers. The procedure was similar to that outlined above for the vegetated riprap brush layer in section 1.

A trench was first excavated in the road sub-grade behind the placed riprap, followed by:

1) Placement of live cuttings in the trench.
2) Watering and addition of soil amendments.
3) Backfilling of the trench using topsoil and native soil material.
4) Placement of protective wooden sheets.
5) Placement of riprap to complete the road sub-grade.
 
 

In Section 2, a mechanically stabilized earth (MSE) wall was constructed above the vegetated riprap (see photos below).

 

In Section 1A, a strip of burlap was placed over the riprap prior to placement of the live cuttings as added protection and to better hold the soil before placement of the protective wooden sheets.

 
Excavated trench Section 2 vegetated riprap
fall 2006

Excavated trench Section 2 vegetated riprap

Live cuttings placed in trench

Live cuttings placed in trench

 
Back-filling trench

Back-filling trench

MSE wall constructed above vegetated riprap, cobbles were later placed over wooden sheets

MSE wall constructed above vegetated riprap, cobbles were later placed over wooden sheets

   
Excavated trench for Section 1A and placement of cuttings, spring 2008

Excavated trench for Section 1A and placement of cuttings, spring 2008

Live cuttings placed in trench with burlap

Live cuttings placed in trench with burlap

 
Trench back-filled and sand placed over live cutting on riprap

Trench back-filled and sand placed over live cutting on riprap

Trench back-filled to final sub-grade

Trench back-filled to final sub-grade

 
Completed road

Completed road

 

Survival and Growth:

 

The survival and growth of vegetated riprap brush layers installed along the riverbank has been excellent to date. The survival of the lowest rows of live pockets installed in Section 1 has been poor, due to a prolonged flooding period in the spring of 2006 and 2007. Survival of the upper rows has, however, been relatively good. In areas where the cuttings remained above the water during flooding, survival has been good.

 

Link to: Main Riverbank Restoration Project Page

 
Lower pockets in Section 1 under water during flooding, spring 2006

Lower pockets in Section 1 under water during flooding, spring 2006

Section 1 summer, 2006

Section 1 summer, 2006

 
Section 1, summer 2006

Section 1 summer, 2006

Section 1, summer 2008

Section 1, summer 2008

 
Section 1, summer 2008
Section 1, summer 2008

Section 1 summer, 2008

 
Section 1 South, summer 2010

 
Growth on live cutting planted in riprap, 2010
(note: original live cutting in red circle)

Salix lasiandra clump growth 2010

 
Section 1 North, summer 2010
 
Section 2 during flooding, spring 2007, note upper portion of cuttings above water level

Section 2 during flooding, spring 2007, note upper portion of cuttings above water level

Section 2 during flooding, spring 2007, note upper portion of cuttings above water level

 
Section 2, summer 2008

Section 2 summer, 2008

Section 2, summer 2008

 
Section 2, summer 2008

Section 2, summer 2008

Section 1A, spring 2008

Section 1A, spring 2008

 
Section 1A, summer 2008

Section 1A, summer 2008

 
Section 1A South, summer 2010
 
Section 1, summer 2010

 
Section 1A, summer 2010

 
Section 1, 1A and 2, summer 2010

 
Section 1 Fall 2014

Section 1 Fall 2014

Section 1 Fall 2014

Section 1A Fall 2014

 
Section 1 pocket 2014

 
Section 3 Fall 2014

Section 3 Fall 2014

 
Before, 2006

 
Hillside Fall 2014

home

Copyright © 2010 Terra Erosion Control Ltd.

Vegetated Riprap