Dewatering of Sensitive Riparian
Area at the Wolf Willow Ravine Work Site / Storm Water
Outfall 13 City of Edmonton
OUTFALL
13
Location:
Storm
water Outfall 13 at the mouth of Wolf Willow Creek Ravine,
flowing into the North Saskatchewan River, City of Edmonton,
Alberta
Client:
City
of Edmonton
Objective:
Dewatering
of work site within sensitive riparian areas using coffer
dams and a sediment settling pond system.
In
the fall of 2008 Terra Erosion Control, working in conjunction
with Kitchton Contracting 1963 Ltd, armoured the banks
of Wolf Willow Creek Ravine surrounding Outfall 13 using
a riprap application (see main project: City
of Edmonton-Outfall 13).
In
order to comply with the Department of Fisheries and
Ocean’s (DFO) regulations prohibiting activities resulting
in sediment laden water entering fish habitat, the work
areas upstream and downstream of Outfall 13 needed to
be dewatered.
The
dewatering of Outfall 13 encompassed the following measures:
- Coffer
dams using nylon bags filled with clay material were
built across the creek channel upstream of the work
area and at the discharge of Outfall 13.
-
A
sediment settling pond lined with geotextile was
located below the work area.
-
A
sediment barrier was constructed using a combination
of straw bales and silt fencing and located across
the channel at the mouth
Initially,
the water pooling below the outfall outlet was pumped
out directly into the sediment settling pond prior to
proceeding with the rehabilitation work. The water held
behind these coffer dams was then drained by gravity
through 4” plastic pipes into the sediment settling
pond. While excavation and riprap placement took place
within the channel upstream from the outfall outlet,
water was pumped from the upstream coffer dam into the
coffer dam located within the outfall structure.
The
plastic pipes used for drainage were passed through
a culvert located within the access ramp (built to provide
access to the channel). The water discharged from the
sediment settling pond was then filtered through a sediment
barrier before entering the North Saskatchewan River.
All structures were removed after project completion.
This
system has proven very effective at dewatering the work
area and reducing sediment delivery into the North Saskatchewan
River. As the work was carried out late in the
year, problems associated with water freezing in the
plastic pipes was encountered toward the end of the
project.
|