.... Specialising in reducing accelerated erosion

Live Pole Drain Systems

SHEEP CREEK LIVE POLE DRAIN SYSTEM

Location: Salmo, British Columbia, along the Sheep Creek Road.

Client: Ministry of Transportation and Highways (MOTH)

Objective:  To restore stability of the slide site using soil bioengineering structures and provide drainage of surface and subsurface seepage water using live pole drain systems.

 

The debris slide and earth flow at the Sheep Creek failure site originally occurred between the fall of 1998 and the spring of 1999.

 

Gradients on the slide face range from 80 to 150% and from 30 to 60% on the debris at the toe of the slide. The material is primarily glacio-lacustrine inbedded silt and sand with some clay. The glacio-lacustrine materials are overlain by glaciofluvial sand and gravel. The glaciofluvial materials are dry and well to rapidly drained. The glacio-lacustrine materials are poorly drained and include extensive areas of seepage. The water table is perched on silt and clay layers in a number of locations.

 

Live pole drain (LPD) systems, which included lateral drain fascines, were installed in four natural drainage / seepage channels within the slope failure area in the spring of 2001 (other structures installed at the same time are discussed in the Sheep Creek project page). The central pole drains were constructed using cylindrical bundles of live cuttings approximately 30 cm in diameter and using the lateral drain fascines bundles of approximately 15 to 20 cm in diameter. The live cuttings used consisted of a mix of Willow species (Salix bebbiana / scouleriana / exigua), Black Cottonwood (Populus balsamifera ssp. trichocarpa), and Red-Osier Dogwood (Cornus stolonifera). The structures were secured on the slope using steel “T” re-bars.

 

The site was monitored from 2003 to 2005. The site showed fully functioning live pole drain systems, draining surface & subsurface seepage water into the ditch line adjacent to the road and good overall growth of the establishing vegetation.

 
Sheep Creek site before treatment, April 2001

Sheep Creek site before treatment, April 2001

Installing LPD system in foreground, 2001
Installing LPD system in foreground, 2001
Installing LPD system

Installing LPD system

Installing LPD system

Installing LPD system

 
Location of four LPD systems installed

Location of four LPD systems installed

 
Site June 2001

Site June 2001

Site later in 2001

Site later in 2001

 
Site in 2003

Site in 2003

Site in 2003

Site in 2003

 
Site in 2004

Site in 2004

Site in 2004

Site in 2004

 
Site in 2005

Site in 2005

Site in 2005

Site in 2005

 

home

Copyright © 2010 Terra Erosion Control Ltd.

Live Pole Drains