.... Specialising in reducing accelerated erosion

Reclamation of Contaminated Lands Adjacent to Lead-Zinc Smelter

COMINCO DUNCAN SLOPE PHASE III and IV

Link to:

Phase I and II

Location: Adjacent to Lead-Zinc Smelter in Trail, BC

Client: Teck Cominco Metals Limited

Objective: Reclaim contaminated land adjacent to lead-zinc smelter by capping with soil suitable for plant growth. Control accelerated soil erosion and establishment of native vegetation.

The Duncan Slope Phase III and IV project area covers approximately 1 ha. The site is located immediately adjacent to the Phase I and II project area and was therefore subjected to similar levels of sulphur fumigation and metal depositions from the smelter. In 2005 Terra Erosion Control Limited was retained to develop and implement a reclamation prescription for this area. Katherine A. Enns, RPBio., M.Sc., PBiol., Delphinium Holdings Inc., collaborated in development of the planting prescription and is using this area as a research site.

 

In March 2006 a sandy-loam soil capping material was placed to a depth of approximately one meter over the Phase III area. Prior to soil spreading, lime was applied to the site to ameliorate the highly acidic native soil condition.

 

Composted biosolids from the Celgar pulp mill in Castlegar was used as an organic amendment in the soil capping material applied to the top 0.3 meters. The quantity of biosolids used was calculated so as to obtain 7.5 % organic matter in this surface layer.

 

After soil placement using a small bulldozer, the machine tracked up and down the slope to create cleat marks (surface roughness) for seed microsites and rain catchment. Straw wattles were also installed across the slope to control surface erosion until grasses became established. The site was seeded with native grasses, using both bunch forming and sod forming species, along with legumes. The seed mix was developed by Dave Polster R.P.Bio of Polster Environmental Services Ltd.

 

Phase IV, which was simply the completion of a small area not finished in March (Phase III), was completed in October 2006.

 

A variety of native coniferous, deciduous trees and shrubs were planted in the fall of 2006. Grass/brush mats were installed around seedlings during planting to help reduce grass competition.

 

During the composting process the biosolids used on this project became heavily infested with weed seeds (windrows were not covered). This resulted in heavy weed growth on the site, necessitating an intensive hand weeding treatment in June 2006.

 

Grass cover was very good in the spring of 2007, which effectively stopped soil erosion from the site. Survival of the planted seedlings was, however, very poor.

 
 
 

 

 

 

Phase III and IV area
September 2005 prior to treatment

Phase III and IV area in September 2005

 

Phase III and IV area, September 2005

Phase III and IV area in September 2005

 
Phase III and IV area, September 2005
Phase III and IV area in September 2005
Phase III and IV area, September 2005

Phase III and IV area in September 2005

   
 
Lime application prior to soil placement, March 2006
Lime application prior to soil placement, March 2006
Overview of site March 2006. On left side 0.7 m of soil capping base was placed. On right side soil placement was not completed

Overview of site March 2006. On left side 0.7 m of soil capping base was placed. On right side soil placement was not completed

   
 
Composted biosolids used as soil amendment

Composted biosolids used as soil amendment

Mixing of soil and biosolids for surface layer
March 2006

Spreading organic-enriched surface layer, March 2006

 
Spreading organic-enriched surface layer
March 2006

Spreading organic-enriched surface layer, March 2006

Soil spreading completed with bulldozer tracking March 2006

Soil spreading completed with bulldozer tracking, March 2006

 
Slope with straw wattles installed, March 2006

Slope with straw wattles installed, March 2006

Hand weeding, June 2006

Hand weeding, June 2006

 
Site after weeding completed, June 2006

Site after weeding completed, June 2006

Site in September 2006, Phase III area in foreground, Phase IV area in background
(no grass cover here)

Site in September 2006, Phase III area in foreground, Phase IV area in background (no grass cover here)

 
Planting trees and shrubs, September 2006
Planting trees and shrubs, September 2006
Tree planted with grass mat

Tree planted with grass mat

 
Site spring 2007
Site spring 2007

 

 

home

Copyright © 2010 Terra Erosion Control Ltd.

Contaminated Lands Reclamation ~ Lead Zinc Smelter